SH 195 Project 3

Location

South of Ronald W. Reagan Blvd. to IH-35

Description Reconstruction of existing two-lane facility to a four-lane divided facility.
Status TxDOT managed the design, environmental clearance and construction. Construction contract was awarded to SEMA Construction.  TxDOT reconstructed the existing two-lane facility to a four-lane divided facility.  A groundbreaking was held on February 11, 2013, and construction reached substantial completion in July 2015.  
Contact Email roads@wilco.org or phone 512-943-3370

Project Map


View Larger Map

Preliminary - Subject to Change