IH 35 Frontage Road Conversion and Ramp Reversals

Location IH-35 from Bud Stockton Loop south of Jarrell, TX to the FM 972 Overpass north of Georgetown, TX
Description The project will implement the conversion of two-way frontage roads to one-way and the removal and reconstruction of existing IH-35 ramps within the project limits.
Status

Design underway by Binkley & Barfield. Construction will be scheduled once state or federal funding has been identified. An open house was held on Thursday June 30, 2016, presenting proposed improvements to CR 305 at I-35, Ronald Reagan Blvd. at I-35, and Frontage Roads between Bud Stockton Loop and FM 972 in Jarrell, TX. A summary of the open house can be found under Project Documents. 

Waterline - Design of the relocation of the 48" Williamson County Regional Raw Waterline (WCRRWL) has been completed by Cobb Fendley. Construction is anticipated to begin in late 2017. 


Project Map

To view a larger version click the picture.